Sunshine Portal · Section
Department of Transportation
All Budgets departments for FY2027. Click a department to drill into its funds.
Sunshine Portal · Section
All Budgets departments for FY2027. Click a department to drill into its funds.
505 departments in Department of Transportation. Click a department to drill into its funds.
| Department | Funds | Approved Budget | Adjusted Budget | Total Expenditures | Budget Balance |
|---|---|---|---|---|---|
| All | 17 | $3,198,901,717.98 | $4,446,448,399.27 | $851,149,737.14 | $3,595,298,662.13 |
| ALB SOUTHWEST MESA STREET LIGH | 1 | $308,671.61 | $308,671.61 | $20,884.78 | $287,786.83 |
| E MADRID AVE IMPROVE LAS CRUCE | 1 | $305,538.72 | $305,538.72 | $305,538.72 | $0.00 |
The New Mexico Sunshine Portal was created pursuant to the Sunshine Portal Transparency Act, NMSA 10-16D-1 et. seq, to provide public access to state government budgets, expenditures, revenue and specific public school district information, and to make such information accessible on one central website. The Sunshine Portal Transparency Act was enacted by the Fiftieth Legislature, First Session and signed into law by Governor Susana Martinez on March 30, 2011. The web site will be updated monthly, the currency of the data will be published on each information panel.
| 1 |
| $300,000.00 |
| $300,000.00 |
| $0.00 |
| $300,000.00 |
| ALB NE MEDIANS IMPROVE | 1 | $300,000.00 | $300,000.00 | $0.00 | $300,000.00 |
| ALB TRAFFIC-CALMING TECH EQUIP | 1 | $300,000.00 | $300,000.00 | $0.00 | $300,000.00 |
| BADGER LOOP/N9505 PLAN | 1 | $300,000.00 | $300,000.00 | $0.00 | $300,000.00 |
| BARCELONA RD STORM DRAIN CONST | 1 | $300,000.00 | $300,000.00 | $0.00 | $300,000.00 |
| BERN CO EAST MT ROADS CONSTRUC | 1 | $300,000.00 | $300,000.00 | $0.00 | $300,000.00 |
| DAVIS ST & GUNDERSON RD CONSTR | 1 | $300,000.00 | $300,000.00 | $270,124.82 | $29,875.18 |
| DESERT WIND WAY IMPROVE | 1 | $300,000.00 | $300,000.00 | $299,996.98 | $3.02 |
| DONA ANA CO PICACHO HILLS AREA | 1 | $300,000.00 | $300,000.00 | $108,333.86 | $191,666.14 |
| DONA ANA CO RADIUM SPRINGS I-2 | 1 | $300,000.00 | $300,000.00 | $0.00 | $300,000.00 |
| FOOTHILL RD SW DESIGN | 1 | $300,000.00 | $300,000.00 | $70,373.47 | $229,626.53 |
| GONZALES RD CONSTRUCT | 1 | $300,000.00 | $300,000.00 | $0.00 | $300,000.00 |
| GRECIAN AVE STORM WATER DRAIN | 1 | $300,000.00 | $300,000.00 | $0.00 | $300,000.00 |
| IYANBITO CHP BNSF CROSSING CO | 1 | $300,000.00 | $300,000.00 | $0.00 | $300,000.00 |
| MCKINLEY CO EMERGENCY BRIDGE R | 1 | $300,000.00 | $300,000.00 | $0.00 | $300,000.00 |
| MENAUL BLVD IMPROVE | 1 | $300,000.00 | $300,000.00 | $0.00 | $300,000.00 |
| ROSWELL CITY STREETS REPAIR | 1 | $300,000.00 | $300,000.00 | $299,035.13 | $964.87 |
| S COORS BLVD LIGHTING CONSTRUC | 1 | $300,000.00 | $300,000.00 | $0.00 | $300,000.00 |
| SAN PEDRO DR NE IMPROVE | 1 | $300,000.00 | $300,000.00 | $0.00 | $300,000.00 |
| SOUTHWEST SWA VEH & EQUIP PRCH | 1 | $300,000.00 | $300,000.00 | $0.00 | $300,000.00 |
| SUNSET RD SW IMPROVE | 1 | $300,000.00 | $300,000.00 | $0.00 | $300,000.00 |
| WILLOW DR & PINON ST DESIGN | 1 | $300,000.00 | $300,000.00 | $300,000.00 | $0.00 |
| PUEBLO ALTO/MILE HI STORM WATE | 1 | $290,000.00 | $290,000.00 | $0.00 | $290,000.00 |