Purchase orders that Department of Environment has placed with TOWN OF VAUGHN for FY2027. Click a PO to see line items and detail.
Data as of: September 30, 2026Updated: October 14, 20262 records
- # of Purchase Orders
- 2
- Total Amount
- $438,568.67
- Balance
- $12,348.79
Purchase Orders
2 POs with TOWN OF VAUGHN at Department of Environment. Click a PO ID to see its line items.
FY2027 · Executive
Filters
| PO ID | Description | Contract ID | PO Date | Total Amount | Amount Expended | Balance |
|---|---|---|---|---|---|---|
| — | — | — | — | $438,568.67 | $426,219.88 | $12,348.79 |
| 0000047896 | Replace Floor- subgrade exchange, new shell manway, repair holes, new vents, upgrade level gauge. Coat interior and exterior, concrete foundation and steel foundation ring. RIP 00071- Town of Vaughn. | — | 07-07-2026 | $430,000.00 | $417,651.21 | $12,348.79 |
| 0000048417 | plan, design, construct, purchase, equip and install water system improvements, including water meters, Grants & Services - SAP 25-J4149-STBR (Severance Tax Bond Re-authorized) Town of Vaughn | — | 09-23-2026 | $8,568.67 | $8,568.67 | $0.00 |
Showing 1 to 2 of 2 entries