Sunshine Portal · Section
CDM SMITH INC
Purchase orders that Ofc of the State Engineer has placed with CDM SMITH INC for FY2027. Click a PO to see line items and detail.
Data as of: September 30, 2026Updated: October 14, 20265 records
- # of Purchase Orders
- 5
- Total Amount
- $1,496,544.00
- Balance
- $1,401,364.36
Purchase Orders
5 POs with CDM SMITH INC at Ofc of the State Engineer. Click a PO ID to see its line items.
FY2027 · Executive
Filters
| PO ID | Description | Contract ID | PO Date | Total Amount | Amount Expended | Balance |
|---|---|---|---|---|---|---|
| — | — | — | — | $1,496,544.00 | $95,179.64 | $1,401,364.36 |
| 0000027439 | Design and Construction Phase 3 - Cimarroncito Dam, Cimarroncito Spillway Dam Phase 3 - 65% FEMA HHPD Grant, Cimarroncito Spillway Dam Phase 3 - 35% NM Match Grant | 0000000000000000000026121 | 09-22-2026 | $798,380.00 | $0.00 | $798,380.00 |
| 0000027381 | Task to perform the Cimarroncito Dam rehabilitation design Phase 2 | 0000000000000000000024790 | 08-26-2026 | $490,884.65 | $71,979.71 | $418,904.94 |
| 0000027380 | Initiate the design effort for the rehabilitation of Cimarroncito Dam Colfax County | 0000000000000000000024790 | 08-26-2026 | $107,279.35 | $23,199.93 | $84,079.42 |
| 0000027438 | Investigation and Panning Engineering Analysis on Dam Deficiencies and other Technical Tasks Required by Office of the State Engineer-Dam Safety Bureau | 0000000000000000000026120 | 09-22-2026 | $50,000.00 | $0.00 | $50,000.00 |
| 0000027440 | Dam Inspections and Program Support | 0000000000000000000026122 | 09-22-2026 | $50,000.00 | $0.00 | $50,000.00 |
Showing 1 to 5 of 5 entries