Data as of: September 30, 2026Updated: October 14, 20268 records
- # of Purchase Orders
- 8
- Total Amount
- $19,300,095.73
- Balance
- $19,300,095.73
Purchase Orders
8 POs with MOUNTAIN STATES CONSTRUCTORS I at Department of Transportation. Click a PO ID to see its line items.
FY2027 · Executive
Filters
| PO ID | Description | Contract ID | PO Date | Total Amount | Amount Expended | Balance |
|---|---|---|---|---|---|---|
| — | — | — | — | $19,300,095.73 | $0.00 | $19,300,095.73 |
| 0000442412 | 007 - ASPHALT BINDER, PG 58-282222 TONS X $800.00 = $1,777,600.00 | 50805002517134AB | 09-03-2026 | $6,896,213.84 | $0.00 | $6,896,213.84 |
| 0000442402 | 007- ASPHALT BINDER, PG 58-281866 TON X $800.00 = $1,492,800.00 | 50805002517134AB | 09-03-2026 | $6,096,131.30 | $0.00 | $6,096,131.30 |
| 0000440026 | ITEM# 2 Minor Paving Type I SP-III Contractor Furnished HMAMill and Inlay I-40 mm 60.1 to 63.114103 TONS @ $96REQUESTED BY EUGENE HOSTEEN | 30805002216977AF | 07-23-2026 | $1,877,737.24 | $0.00 | $1,877,737.24 |
| 0000442827 | 016 - HMA PAVEMENT SP-IV PG 76-22, 3" LIFT, COMPLETE IN-PLACE WITHIN DISTRICT 1. ESTIMATED QUANTITIES: 50,001 SQ. YDS. AND OVER50,281 SQ YD X $19.00 = $955,339.00 | 40805002317044AD | 09-14-2026 | $1,584,828.08 | $0.00 | $1,584,828.08 |
| 0000442702 | 007 - ASPHALT BINDER, PG 58-28259 TON X $800.00 = $207,200.00 | 50805002517134AB | 09-10-2026 | $1,188,786.80 | $0.00 | $1,188,786.80 |
| 0000440394 | ITEM# 1 Minor Paving Type I SP-III Contractor Furnished HMAI-40 mm 54 to 56.5 Mill and Inlay5820 TONS @ $105 9/16/2026 INCREASE TO 6130.12 LF @ $105REQUESTED BY EUGENE HOSTEEN | 30805002216977AF | 07-30-2026 | $901,228.64 | $0.00 | $901,228.64 |
| 0000442492 | 038 - TRAFFIC CONTROL LANE CLOSURE 45 MPH AND OVER: PER WEEK SEVEN (7) DAY PERIOD12.60 WEEK X $14,700.00 = $185,220.00 | 40805002317044AD | 09-08-2026 | $524,820.15 | $0.00 | $524,820.15 |
| 0000442901 | 017 - HOT MIX ASPHALT SP-III PG 70-22, 2 1/2" LIFT, COMPLETE IN-PLACE WITHIN DISTRICT 1. ESTIMATED QUANTITIES: 0 TO 50,000 SQ. YDS. 1,334 SQ YD X $16.41 = $21,890.94 | 40805002317044AD | 09-15-2026 | $230,349.68 | $0.00 | $230,349.68 |