Sunshine Portal · Section
PO 0000442202
Department of Transportation
PO Details
- PO ID
- 0000442202
- PO Date
- 09-01-2026
- Agency
- Department of Transportation
- Vendor
- CUTLER REPAVING INC
- Contract ID
- 30805002317018
- Division
- 93100
- Vendor ID
- 0000013596
- PO Status
- Dispatched
- Buyer
- 365530.HOL
- Origin
- CON
- Cancel Status
- Approved
- PO Amount
- $446,030.64
Division, PO Status, Origin, and Cancel Status are derived from positional fields in the SHARE PO_EXTRACT file. PO Status (D → Dispatched,C → Cancelled) and Cancel Status (A → Approved, C → Cancelled) translations are inferred from the live Sunshine Portal screens and remain pending DOIT confirmation.
Line Items
9 line items on this purchase order.
| Line Item | Category | Description | Date | Total Amount | Amount Expended | Balance |
|---|---|---|---|---|---|---|
| 1 | Other Services | 006 - 70,001+ PAVEMENT RESURFACING TO INCLUDE HEATING, SCARIFICATION (1 INCH TO 1-1/2 INCH), RECYCLING OF EXISTING PAVEMENT AND MIXING WITH NEW HOT MIX MATERIAL, SPREADING AND COMPACTION IN AREAS WITH CURB AND GUTTER112,634 SY @ $3.96 = $446,030.64 | 09-01-2026 | $446,030.64 | $0.00 | $446,030.64 |
| 2 | Other Services | 011 - CURB LINE COLD MILLING OF ASPHALT SURFACE 50,001+ S.Y.-INCH281,584 SY INCH @ $1.86 = $523,746.24 | 09-01-2026 | $523,746.24 | $0.00 | $523,746.24 |
| 3 | Other Services | 013 - RE-ESTABLISH TEMPORARY CENTERLINE WITH 4 INCH BY 4 FOOT STRIPE WITH 36 FEET SPACING AS DESIGNATED BY THE DISTRICT ENGINEER OR THEIR DESIGNEE7,340 L.F @ $1.35 = $9,909.00 | 09-01-2026 | $9,909.00 | $0.00 | $9,909.00 |
| 4 | Other Services | 014 - RE-ESTABLISH TEMPORARY CENTERLINE WITH REFLECTORIZED TABS AT 40 FEET SPACING OR AS DESIGNATED BY THE DISTRICT ENGINEER OR THEIR DESIGNEE837 EA @ $1.20 = $1,004.40 | 09-01-2026 | $1,004.40 | $0.00 | $1,004.40 |
| 5 | Other Services | 017 - TRAFFIC CONTROL URBAN TO INCLUDE ALL SIGNING AND TRAFFIC CHANNELIZATION DEVICES FOR ADEQUATE HANDLING OF TRAFFIC. URBAN TRAFFIC CONTROL TO BE DEFINED AS REQUIRING SIGN SPACING TO BE 350' OR LESS256 HR @ $300.00 = $76,800.00 | 09-01-2026 | $76,800.00 | $0.00 | $76,800.00 |
| 6 | Other Services | 019 - FLAGGING FOR URBAN AND RURAL TRAFFIC CONTROL. PAYMENT SHALL BE PER FLAGGER PER HOUR.1,024 HR @ $45.00 = $ 46,080.00 | 09-01-2026 | $46,080.00 | $0.00 | $46,080.00 |
| 7 | Other Services | 020 - SEQUENTIAL FLASHING ARROWS / FLASHING DIRECTIONAL ARROWS AS REQUIRED BY THE DISTRICT ENGINNER OR THEIR DESIGNEE256 HR @ $30.00 = $7,680.00 | 09-01-2026 | $7,680.00 | $0.00 | $7,680.00 |
| 8 | Other Services | 029 - MOBILIZATION WITH CURB LINE COLD MILLING263 MILE @ $175.00 = $46,025.00 | 09-01-2026 | $46,025.00 | $0.00 | $46,025.00 |
| 9 | Other Services | 035 - PG 70-22 ASPHALT BINDER FOR ALL DISTRICT ONE PLANTS768 TON @ $1,059.00 = $813,312.00 | 09-01-2026 | $813,312.00 | $0.00 | $813,312.00 |
Showing 1 to 9 of 9 entries